County advances CR10 and CR11 paving to 2026 in $18.55 million plan

Mountrail County Commissioners · August 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioners voted to move CR10 East Phase I and CR11 paving from 2027 to 2026 and approved an estimated $18,549,757.05 for construction and engineering; the board also authorized advertising CR10 West Phase II with a $13,064,345.15 estimate.

Jana Hennessy, Road & Bridge Engineer, recommended moving CR10 East Phase I and CR11 paving forward from 2027 to 2026. The board voted to approve advancing approximately 21.91 miles of CR10/53rd St NW and CR11/67th Ave NW to construction in 2026 at an estimated combined construction and engineering cost of $18,549,757.05. The motion was moved by Commissioner John DeGroot and seconded by Commissioner Wayne Olson and passed unanimously.

The board also approved advertising the CR10 West Phase II Reconstruction Project with estimated construction and engineering costs of $13,064,345.15. The project descriptions in the minutes specify route endpoints and approximate mileages for both CR10 and CR11. Commissioners and engineering staff said the paving schedule and advertising will proceed as planned; no amendments or oppositions were recorded in the minutes.