County engineer reports bridge removals, fiber‑line damage and grant planning
Summary
County Engineer Adam Miller said crews have removed a timber bridge on 130th Street, are taking down a truss bridge, and are coordinating repairs after a fiber line was hit during work. Staff are preparing B45 and Raise Grant bridge plans with a county letting scheduled for July.
Get email alerts on the Roads Bridges topic
No spam. Unsubscribe anytime.
Adam Miller, County Engineer, updated the Board on secondary roads work, reporting that crews completed brushing and blading during recent good weather and that bridge removal work on 130th Street continues. Miller said the timber bridge is gone and the truss bridge is coming down; a fiber line was hit during the work and the county is coordinating repairs.
Miller also reported that office staff are developing plans for the B45 and Raise Grant bridges, that a grant contract is expected soon, and that the first Floyd County letting is set for July. The update did not record specific costs or timelines beyond the July letting target.