City and county officials plan police move to community center; project estimated at about $746,000
Summary
Officials outlined a plan to move the police department into the community center with a current planned budget of roughly $746,000, previous bids as high as $1.6 million and an estimated construction timeline of 6–7 months.
Get email alerts on the Public Safety Facility topic
No spam. Unsubscribe anytime.
City and county leaders reviewed plans to relocate the police department into the community center and discussed project costs, timelines and the effect on dispatch and budgeting.
"We're gonna spend 746,000, and we're hoping to start this, Chase, in late summer, early fall," the Chair said, describing the current cost estimate and target start window. Participants reviewed prior bids: "The initial bids came in on 1,600,000 and 1,300,000. 1,300,000 was the low bid," a commissioner noted, and staff described how scope reductions brought the price down during subsequent discussions.
A county official estimated the construction and transition would take about six to seven months from start to finish, and staff said they expect minimal service disruptions. Commissioners also discussed how to split police and dispatch budget lines in the 2027 budget and requested spreadsheets and line-item breakdowns so each jurisdiction could plan fiscal impact and staffing costs.
Staff committed to share the detailed spreadsheet of projected wages and benefits for dispatch and police to allow the jurisdictions to finalize funding commitments ahead of construction.