Bristow authority approves $195,237 change order for wastewater plant, raising contract to $8.94 million
Summary
Trustees unanimously approved Change Order No. 4 to KBC Construction’s WWTP contract, adding $195,237.81 to the original $8,315,150 and bringing the total to $8,938,406.08.
Get email alerts on the Wastewater Construction topic
No spam. Unsubscribe anytime.
The Bristow Municipal Authority voted on April 7 to approve Change Order No. 4 for KBC Construction, Inc. related to improvements at the city’s Wastewater Treatment Plant. Trustee Judd Johns moved the change order, Trustee Jeff Roberts seconded, and a roll-call vote was unanimous. The change order adds $195,237.81 to the original contract of $8,315,150.00, producing a new total of $8,938,406.08.
Minutes list the original contract amount, the change-order addition, and the new total; they do not specify funding sources or a revised project schedule. The authority’s approval completes the recorded action on this change order at the April 7 meeting.