Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Officials weigh $31.5M–$33.6M options for county building renovation or replacement
Summary
Commissioners discussed three proposals for replacing or renovating the county building: rehabilitation at $33.6M (plus $5M temporary housing), a 5‑story partially finished option at $31.5M, or a fully finished 5‑story building at $33.5M; a referendum is likely to be required.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Commissioner Al Knable presented three costed options for the County building during the June 24 joint meeting and said he favors a fully finished five‑story building for long-term needs.
Knable listed the options: complete rehabilitation of the existing building at $33,600,000 with $5 million for temporary housing; a five‑story building with only four stories finished at $31,500,000; and a five‑story building fully finished at $33,500,000. "I think the 5-story fully finished building would be the best option for this generation of people and generations to come," Knable said, while noting it will probably require a referendum. Commissioner Jason Sharp agreed with Knable's assessment and said the current building condition is embarrassing.
No funding decision or referendum was scheduled at the meeting; officials indicated the animal shelter site as a potential location and asked for continued planning and coordination.
