Harris County proposes 1,100-acre-foot Genoa Red Bluff detention project at $55 million
Summary
Staff said Harris County is moving a Genoa Red Bluff detention project into bidding with proposed capacity of about 1,100 acre-feet and an estimated cost of $55,000,000; staff said the work will be south of Fairmont Parkway and will offer some benefit to La Porte.
Get email alerts on the Genoa Red Bluff topic
No spam. Unsubscribe anytime.
Ray Mayo told the committee that Flood Control has funded a large Genoa Red Bluff detention-area project and is preparing it for bids. "It's gonna be a large, large project that they've proposed, 1,100 acre feet at a cost of $55,000,000," Mayo said, and added the site is just south of Fairmont Parkway with potential benefits to La Porte.
Mayo said he will bring a map to the next meeting showing phasing and locations. Committee members asked follow-up questions about where excavation material would be taken; staff said they did not yet know disposal plans but agreed to track the information and report back.