Commissioner reports final courthouse walkthrough; first-floor renovation quoted at $227,000
Summary
Commissioner Dan Borgenheimer reported a final walkthrough on courthouse construction with window sealing still outstanding and presented first-floor renovation quotes totaling $227,000.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Commissioner Dan Borgenheimer reported a final walkthrough of the ongoing courthouse construction and said crews still need to finish window sealing. He also presented contractor quotes for renovating the courthouse first floor that together total $227,000.
Borgenheimer did not present a funding source or ask for an immediate vote during the May 7 meeting; the update was informational. Council members will consider next steps and potential transfer or appropriation requests in subsequent meetings if funding is required.