Commission reviews arena closeout; moves to solicit bids for incorrect bleacher panels when specs corrected

Geneva County Commission · June 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Geneva County reported construction at the new multi-purpose arena is complete and is awaiting final closeout documents; commissioners authorized soliciting bids for arena panels once corrected specifications are received and discussed procurement rules for projects over $100,000.

Chairman Toby L. Seay said all construction work on the county's multi-purpose arena is complete and that final closeout documents and advertisement were pending. Seeding, mulching and border work were finished, and the contractor and Road & Bridge were to inspect rain-related washing issues; Seay said he expects quotes for bleachers by the next meeting.

County Attorney Phil Eldridge advised the Commission that the procurement will likely fall under the definition of a general contractor when the cost exceeds $100,000, citing Administrative Code rule 230-X-1-.09: "in determining the amount of a contract, labor and material cannot be separated." Commissioner Jeff Hatcher moved to put the panels out for bid once correct specifications are received; the motion passed 3-0.