Facility manager requests review of Havel contract, cites HVAC failures and landscaping needs
Summary
Facility Manager Megan Westfall asked commissioners to delay payment to Havel, saying the firm has not performed preventative maintenance; she reported first‑floor HVAC failures, landscaping problems and will submit quotes for remedying courthouse grounds.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Facility Manager Megan Westfall told the board she received an invoice from Havel but requested that payment be delayed because "Havel has not been doing any preventative maintenance." She said one year remains on Havel’s contract and that she will forward the contract to County Attorney Jim Forcum for review; Havel remains the only vendor authorized to work on the building controls, per the transcript.
Westfall also reported Resolve Tech repaired leaks in the Circuit courtroom and portions of the third floor, but that first‑floor HVAC is not working. She asked the commission to allow staff to solicit quotes from other HVAC contractors to service all units and said the courthouse lawn needs grading and shrub removal; she plans to obtain a quote from Top Notch for presentation at the next meeting.