Council asks Bollig to revise Task Order #8 and reviews $230,000 design work for well and wellhouse
Summary
The council reviewed Bollig Task Orders #8 ($5,000/year + 5% funding secured) and #9 ($230,000 for well/wellhouse design), asked Bollig to remove percentage-based fees from #8, and requested review of task order standards in the engineering master agreement.
Get email alerts on the Bollig Task Orders topic
No spam. Unsubscribe anytime.
The Wrenshall City Council considered two Bollig task orders during its June 22 special meeting. Task Order #8 for funding application and administration was listed at $5,000 per year plus a fee equal to 5% of funding secured; Task Order #9 for well and wellhouse design was listed at $230,000.
Councilors requested that Bollig revise Task Order #8 to remove percentage-based fees and directed that task order standards and protocol under the engineering master agreement be reviewed. The minutes do not record a vote or adoption of the task orders; they record direction to revise and to review standards.
The minutes do not specify a deadline for revisions or which official will review the engineering master agreement; implementation steps and approvals remain pending.