Commissioners approve GMP amendments on Fayette County water treatment project
Summary
The board accepted two amended guaranteed maximum price amendments from Bowen Engineering: $13,355 for Phase 3 compressor ductwork and $386,618.04 for Phase 5/5A air release valve and corporation stop replacements, updating contract totals for the respective phases.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Fayette County commissioners on Feb. 23 accepted two amended Guaranteed Maximum Price (GMP) amendments from Bowen Engineering Corporation relating to the county water treatment plant contracts.
The Phase 3 amendment adds $13,355.00 to cover modifications to the PAC Auxiliary Building compressor ductwork, increasing that contract amount to $8,583,027.00. Separately, the Phase 5/5A amendment adds $386,618.04 to fund air release valve replacements and brass corporation stop replacements required by the City of Wilmington, changing the affected contract amount to $857,627.20 for that amendment. Both amendments were approved on unanimous roll call.