Contractor pours concrete on Geneva County multi-purpose arena; completion projected in early April
Summary
Engineer Justin Barfield reported that work continues on the county multi-purpose arena and that the contractor is pouring concrete. The county projects completion in the first week of April.
Get email alerts on the Multi Purpose Arena topic
No spam. Unsubscribe anytime.
The Geneva County Commission received an update that the contractor on the county multi-purpose arena is actively pouring concrete and that the county is projecting a completion date in the first week of April. Engineer Justin Barfield provided the construction status during the meeting.
No new change orders or additional funding requests were reported in the minutes. The commission will continue to monitor construction progress through its regular staff updates and future meetings.