Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure topic

No spam. Unsubscribe anytime.

Roberts Cove Road bridge finished 11 days early and under budget, DPW reports

Alton Board of Selectmen · July 29, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The DPW reported the Roberts Cove Road bridge replacement opened ahead of schedule and came in under the $400,000 authorized budget. Final reported cost: $399,908.67 after a $14,620 change order and $10,288.67 in additional materials.

The Department of Public Works summarized the Roberts Cove Road bridge replacement, which opened to traffic following a short closure that began July 6. The project team removed the old concrete bridge, set new precast sections and placed approximately 1,650 square feet of asphalt on July 16; the road was reopened the following morning.

DPW staff said the job was completed in eight working days (10 calendar days), 11 days ahead of the originally scheduled calendar, and that the combined contract, change order and additional materials produced a final project cost of $399,908.67—$91.33 under the $400,000 figure discussed in packet materials. The board thanked DPW staff and the contractor for completing the project quickly and safely; Selectmen noted the work provided useful experience for staff and added long-term infrastructure benefit.