Lyndon Station approves Change Order No. 3, manhole replacement and draw request for WWTP project
Summary
The board approved Change Order No. 3 for the wastewater treatment plant project, accepted Allen Steele's manhole replacement quote, approved a draw request for WWTP bills and approved the CMAR; all motions passed unanimously.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
At the June 8 meeting the Board addressed several items related to the Village wastewater treatment plant (WWTP) project. President Bob Darnell moved to approve Change Order No. 3; the motion passed unanimously. The Board also approved Allen Steele's quote for manhole replacement and authorized a draw request to pay WWTP project bills.
Trustee Jan Miller moved to approve the CMAR (Capacity, Management, Operation and Maintenance report) and the motion carried unanimously. These approvals advance the WWTP project's contract administration and enable contractor payments to proceed under board authorization.