Engineer: move chlorination downstream of booster pumps to stop corrosion and repeated failures

Eureka City Council · February 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City engineers told the council chlorinated water passing through booster pumps is corroding stainless-steel components; the proposed scope includes replumbing the chlorination system to inject chlorine after pumps to reduce replacements.

An engineering consultant told the council the repeated pump failures are linked to the chlorination point in the system: highly chlorinated water is passing through stainless-steel pump components and causing premature failure.

"Your chlorine is getting injected into the water below the booster pumps and then passing directly through those, which ... is what's causing them to to break down," the consultant said. The proposed corrective work would replace damaged pumps and valves and re-plumb the chlorination system so chlorine is introduced downstream of the booster pumps. Council members and staff said this design change should reduce the frequency of pump replacements and extend equipment life.

The engineer noted the current configuration likely resulted from repurposing existing building infrastructure during earlier work and that the city has hired a new engineering firm to design a lasting fix.