Council approves emergency resolution to contract for Depot Park and trailhead; construction slated March–November 2026
Summary
Council adopted Resolution 26-04 authorizing the mayor or administrative director to sign depot park and trailhead documents with Shrock Premier Custom Construction, declaring an emergency so state funding could proceed; council noted the project timeline is March–November 2026.
Get email alerts on the Depot Park topic
No spam. Unsubscribe anytime.
Councilmember Rodney Earick introduced Resolution 26-04 authorizing the mayor or administrative director to sign documents with contractor Shrock Premier Custom Construction for the Depot Park and trailhead project. Earick asked council to waive committee and second-reading rules; the council granted both waivers and adopted the resolution by roll call vote, 7–0.
Council discussed the schedule and funding timeline; officials said the resolution was moved into the current period at the state’s request to enable state funding. The resolution documentation declares an emergency to allow signing without the usual waiting period, and council noted the project is scheduled to begin in March and conclude in November 2026.
The contract specified in the resolution will be executed by the mayor or administrative director as authorized by the council. No detailed dollar amounts were read into the record during the meeting transcript.