NRD outlines five paths for Bone and Long Pine watershed project as NRCS funding is held up
Summary
Middle Niobrara NRD distributed five potential paths to move WSF #5323 forward and said NRCS funding remains on hold; Chandler Schmidt said he preferred “option A” to place structures now while MNNRD General Manager Mike Murphy urged caution about design-focused spending without construction funds.
Get email alerts on the Wsf Project topic
No spam. Unsubscribe anytime.
The Middle Niobrara Natural Resources District presented five potential approaches to advance Water Sustainability Fund project WSF #5323 for the Bone and Long Pine Watershed Improvement, but presenters said Natural Resources Conservation Service (NRCS) funding is currently on hold.
Chandler Schmidt, representing the MNNRD, distributed a handout outlining the five options and said he preferred "option A" because "it would get a couple structures on the ground." Schmidt told commissioners the MNNRD board and staff will review the alternatives and pick a path at an upcoming board meeting.
MNNRD General Manager Mike Murphy warned the commission about concentrating available funds on a broader, comprehensive design package when there is no immediate funding for construction. Murphy reminded commissioners of past PL-566 watershed designs that later required long waits to secure construction funding, suggesting the commission weigh near-term buildable outcomes against larger design goals.
The commission did not take a formal funding action at the Sept. 30 meeting; staff noted the project options and the NRD's intent to make a local decision about next steps.