Court signs off on sheriff's office remodel change orders and OCO; remodel budget expected near $7 million

Rockwall County Commissioners Court · April 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioners received a detailed update on the sheriff's office renovation, including technology and evidence‑storage moves, generator testing and dispatch relocation; the court approved multiple PCOs and an official change order to move owner's allowances into contractor contingency, with an estimated remodel cost near $7 million and furniture estimated at $520,000.

Commissioner Stacy updated the court on progress and remaining tasks for the sheriff's office remodel and the county's third-floor project. He said the team has addressed generator issues, rerouted IT and planned a dispatch move targeted for May 6; evidence storage relocation is seen as a critical gating item.

Stacy said the original budget was about $7.1 million and he expects the project to come in near $7.0 million barring unforeseen conditions; he noted owners' allowances of approximately $290,000 will be moved into the contract and an expected furniture cost of about $520,000 remains to be ordered. "We are not over budget at all," Stacy said, adding that the project is behind schedule by about 90 days.

Later agenda items presented multiple contract actions: terminating the Bridal contract, approving an AIA amendment with Park Hill for additional owner-rep services ($74,000), approving PCOs 19–30 to SCI Construction and adopting Official Change Order No. 1 to reallocate owner's allowances into contractor contingency. Each motion carried 5–0. The court flagged the need for greater clarity on allowances and for internal processes to better handle pay requests and engineer approvals during closeout.

Next steps: staff will finalize the OCO, return with furniture purchase details and continue to track evidence relocation and dispatch relocation milestones.