Program manager says Treasury accepted MYIP amendment; $17.6M allocated of $21M trust

Santa Rosa County Restore Council · June 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Restore program manager reported Treasury accepted amendment No. 3 to the county's multiyear implementation plan, deobligated two projects and added the Blackwater River Effluent Relocation Project; about $17.6 million of $21 million in trust funds are currently allocated.

The program manager told the Restore Council that amendment No. 3 to Santa Rosa County’s multiyear implementation plan was submitted to and formally accepted by the U.S. Department of the Treasury. She said the amendment deobligated two projects — the North Santa Rosa wastewater treatment facility construction and the Yafaal Outfall project — and added the Blackwater River Effluent Relocation Project.

She gave financial context for the plan: “in total, the total allocation of all of the projects within the multiyear implementation plan is about $17,600,000 worth of allocation, for all the projects on that plan, out of the $21,000,000 that we currently have available in the trust funds,” she said. She also reported a Treasury site review of the Tiger Point wastewater treatment facility expansion found the county in full compliance.