The court approved a memorandum of agreement to buy the last right-of-way parcel for Crenshaw Road (contingent on legal review) and authorized construction bidding for Crenshaw Road East; funding will be from a mix of bond issuances per staff.

Commissioners voted March 24 to approve a memorandum of agreement to acquire the final right-of-way parcel for Crenshaw Road and then authorized construction bidding for the Crenshaw Road East project.

Commissioner Stacy said the $5,000 MOA is the last parcel needed to proceed with construction and noted the project had been funded through a combination of bond issues. Brenda (county staff) clarified the parcel purchase will be paid from 2008 bond proceeds with some costs apportioned across later bond funding; she described the overall funding as roughly split between prior ('08) and more recent ('21) bond issuances.

The court approved acting on the MOA contingent on auditor and legal review (motion passed 5–0). The commissioners then voted 5–0 to put construction bidding for Crenshaw Road East out to bid and to advance required engineering contracting steps.

County staff said the next steps are right-of-way acquisition paperwork, finalizing funding sources, and preparing bid documents so that the county can advertise and solicit contractor proposals. The court emphasized that legal and auditor review should sign off on purchase agreements before closing on property acquisitions.