Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Facilities Maintenance topic

No spam. Unsubscribe anytime.

Board approves $437,000 chiller refurbishment to keep central plant operational through summer

Stafford Municipal School District Board of Trustees · March 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved a cooperative contract to refurbish central plant chiller #1 to ensure at least three chillers operate during summer; trustees discussed a five-year parts/labor warranty, repair vs. replacement planning and funding via a maintenance note.

The board approved a contract to refurbish chiller number 1 that serves district campuses after facilities reported two chillers were beyond repair and one was running intermittently.

CFO and facilities staff explained the central plant has five chillers (three water chillers and two air chillers); with two beyond repair and one intermittent, the district needs a third functioning chiller before summer to reliably cool campuses. The board approved a Huntington/Hutton Services refurbishment under the Choice Partners cooperative (quoted at approximately $437,000), to be paid from the capital improvement/maintenance note balance. The presenter said the refurbishment includes a five-year parts-and-labor warranty for the control panel and parts availability is limited for older units.

Trustees discussed timing and contingencies: staff said lead time is three to seven weeks and that the district could temporarily rent ancillary chillers if needed during the refurbishment. A motion to approve the contract passed unanimously.