University Health says Rotomah campus 80% complete, targets early‑2027 opening
Summary
University Health told the Universal City council its Rotomah campus is about 80% complete, will open with a subset of 147 licensed beds and will phase staffing up over 3–5 years; the system emphasized local ownership and reinvestment in community care.
Get email alerts on the Healthcare topic
No spam. Unsubscribe anytime.
University Health representatives updated the Universal City Council on construction progress at the Rotomah campus, reporting roughly 80% completion and target inspections this fall and winter ahead of a projected opening in early 2027. The presenter said the hospital will be a 500,000‑square‑foot campus with a connected 100,000‑square‑foot medical office building and that the opening complement will include about 40 med‑surg beds, 10 ICU beds and mother‑baby services.
"We're at about 80% completion in our current state," the presenter said, adding that the campus will open with 147 licensed beds overall but not all will be staffed at day one. He said the campus will include a 28‑bed emergency department, operating rooms and neonatal intensive‑care capacity. Council members asked whether patient rooms would be private; the presenter confirmed that all rooms will be private.
University Health also told the council the project represents a roughly $1.5 billion investment across new hospitals and multispecialty clinics and that about 75% of construction work was being performed by local vendors. The presenter said the system plans a small teaching component in collaboration with the University of the Incarnate Word and local clinics. Council members thanked the presenter and noted the campus will expand local access to women's services, STEMI and trauma care.