Council ratifies change orders, authorizes slip‑lining contract for Liberty Grove sewer emergency; project ahead of schedule
Summary
Council ratified $361,599 in change orders to Circle H and authorized a Vortex contract not to exceed $643,510 for slip‑lining and additional work on the Liberty Grove sewer emergency; staff reported the project is about $6.1M to date and running roughly a month ahead of earlier estimates.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Christophe Bauer (speaker 26) updated council on the Liberty Grove Sewer Line Replacement emergency project and requested ratification of change orders to Circle H Contractors (approximately $361,599.01) and authority to enter a contract with Vortex for slip‑lining and related Phase 2 work not to exceed $643,510. Bauer said the original broad estimate of $10–$14 million has been refined and the updated total is approximately $6.1 million due to a mix of replacement, slip‑lining and in‑house pavement work.
Bauer explained the technical approach: a limited replacement of roughly 100 linear feet where a break occurred, installation of a new manhole and then slip‑lining the remainder (a pipe‑in‑pipe technique that can extend service life 40–50 years). City crews took on additional paving and overlay work, generating a credit in the contract and accelerating timelines. Bauer said intersections at Chiesa/Homestead/Liberty Grove should be reopened in the coming days and the full project is expected to be substantially complete by the end of September, a month ahead of prior expectations.
Council thanked public works crews and contractors. A motion to ratify the change orders and authorize the Vortex contract was approved unanimously.