Funding for Red Ball Trail wooden bridge not yet memorialized with ICC or railroad; engineer to meet both parties
Summary
Highway Engineer Mike McCormick told the Bond County Board that funding for the Red Ball Trail Wooden Bridge Project had not been memorialized with the Illinois Commerce Commission and the County had no written agreement from the railroad; he scheduled a meeting with both next Tuesday and said a public hearing will follow.
Get email alerts on the Red Ball Trail Bridge topic
No spam. Unsubscribe anytime.
Highway Engineer Mike McCormick updated the Bond County Board on the Red Ball Trail Wooden Bridge Project on Nov. 19, 2024, saying the county had not memorialized funding with the Illinois Commerce Commission (ICC) and did not have anything in writing from the railroad, both of which the engineer said are required before moving the project forward. McCormick told the Board he scheduled a meeting with the ICC and the railroad next Tuesday and that he will set a public hearing after those discussions.
McCormick outlined four siting options for the project: build to the east, build to the west, build in the center, or do nothing. He said he hopes to secure funding adequate to cover a worst-case scenario. No vote was taken on project authorization at the Nov. 19 meeting; the transcript records planning steps and the need for external approvals before a public hearing is set.