County engineer outlines Eastridge Road timeline, Kleenburn work; commission approves refill for Road & Bridge operator
Summary
Sheridan County Engineer reported rights-of-way work for Eastridge Road with construction expected in spring and completion by October, Kleenburn plans targeting June, and Red Grade bids opening; the board approved filling a Road & Bridge district operator vacancy.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Sheridan County Engineer Ken Muller told commissioners on Feb. 23 that rights-of-way negotiations for Eastridge Road are underway with construction expected this spring and a target completion by October. He reported Kleenburn (Kleenburn) project plans are progressing with a June target and that Red Grade bids would open the following day.
Muller also announced a resignation in a Road & Bridge district operator position and asked permission to advertise and refill the vacancy. Commissioner Lonnie Wright made the motion to refill the district operator position; the motion passed unanimously. The board did not specify contractor awards or construction start dates beyond the seasonal targets provided by the county engineer.