RiverStreet broadband project far behind schedule; board questions ARPA funding alignment

Board of Supervisors of Nottoway County · July 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Nottoway staff reported RiverStreet has completed roughly 10% of its work (25 of 238.99 miles) though contract amendments required 60% completion by Dec. 31, 2025; the County noted an end‑of‑2026 deadline to meet ARPA guidelines and questioned whether ARPA funds were dedicated to broadband broadly rather than the RiverStreet contract specifically.

Planning & Economic Development staff told the Board that RiverStreet has completed roughly 10% of the network, having laid only 25 miles of an expected 238.99 miles to date. The Fourth Amendment to the contract required 60% completion by Dec. 31, 2025; staff said the current deadline for completion is the end of 2026 in order to meet ARPA guidelines.

Mr. Zody said the 60% milestone was not met and the Board discussed whether the ARPA funds had been dedicated to broadband generally rather than to RiverStreet specifically. No formal enforcement action or new appropriation was recorded at the meeting; staff indicated they will invite RiverStreet to the next EDC meeting to discuss progress.