Pierce County committee approves multiple change orders for new judicial facility, most covered by contingency

Pierce County Ad Hoc Judicial Facility Planning Committee · December 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Ad Hoc Judicial Facility Planning Committee unanimously approved several change orders Dec. 11, 2025; five items carry additional costs totaling $53,098 to be paid from the owner’s contingency, while multiple other adjustments were approved at no cost.

The Pierce County Ad Hoc Judicial Facility Planning Committee on Dec. 11 approved a series of construction change orders for the county’s new judicial facility, with most costs covered from the project owner’s contingency. John Nuzum of Market & Johnson summarized the technical clarifications and coordination changes driving the requests; all motions to approve the listed change orders carried unanimously.

The committee approved several no-cost adjustments (including plan clarifications for state review, civil grade changes at the main drive, EPDM roof assembly upgrades, and footing/foundation alignment). Five change orders called for additional contingency funds: electrical adjustments and an exterior light pole (COR#5, $19,007), lightning protection design and installation (COR#12, $27,115), boiler-loop modifications (COR#18, $3,862), moving two variable-frequency drives (COR#21, $2,594), and beam upsizing for live-load adjustments (COR#6, $520). Those five items total $53,098 and, per the committee record, will be paid from owner’s contingency within Market & Johnson’s contract.

Committee members asked for clearer documentation in future change orders about the purpose or cause of each change. Administrative Coordinator Jason Matthys and others noted the project remains on schedule; pending items (COR#4 and COR#10 on lighting controls and related issues) will return to the committee after further vetting. The meeting adjourned at 12:47 p.m.