City Manager reports Riverfront renovation progress; seawall complete

Gallipolis City Commission · January 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City Manager John Westfall told the Gallipolis City Commission the Riverfront renovation has reached multiple milestones: the seawall is complete, crews are hauling dirt and stone, and rebar is staged to prepare for concrete pours. Work also required removal of monuments and park fixtures.

City Manager John Westfall reported to the Gallipolis City Commission on Jan. 20, 2026, that work at the Riverfront is advancing: “the seawall is complete,” crews are hauling dirt and staging stone and rebar to prepare for concrete pours, and monuments, benches and swings have been removed as part of site preparation. Vice‑President Dr. William "Bill" Thomas called the special meeting to order and heard the update in the presence of commissioners Brown, Carter and Kirby and staff.

The manager said he had an online coordination meeting with contractors and engineers the same day and that the commission is monitoring the schedule as the project moves into concrete work. The report did not include a new completion date or revised budget figures; follow up on schedule and costs will take place during upcoming budget meetings and project briefings to the commission.