Highway supervisor: bridge-deck pour delayed; winter tree removal at county park funded by DNR grant
Summary
Highway Supervisor Brian Koch told the Commission the bridge deck test run was completed Nov. 26 but the pour must wait for warmer weather. He said the county plans tree removal at the county park this winter and will seek quotes; a DNR grant is expected to pay for the work.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
Highway Supervisor Brian Koch reported the bridge deck test run for the pouring deck was completed Nov. 26 and said crews will delay the actual pour until temperatures are suitable for concrete work. Koch told commissioners the county plans to remove trees at the county park this winter and will request quotes for that work.
Koch said the project team expects a DNR grant to cover the park tree-removal expenses. The Board did not take formal action beyond receiving the update and authorizing the solicitation of quotes if required.