Commissioners extend H2O Partners project deadline to Feb. 28, 2029

Burleson County Commissioners Court · May 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Burleson County Commissioners approved Amendment 1 to the county’s H2O Partners contract (originally dated Aug. 11, 2025), setting a project end date of Feb. 28, 2029. The motion passed unanimously on May 11, 2026.

Burleson County Commissioners Court on May 11 approved Amendment 1 to the county’s contract with H2O Partners, Inc., establishing a project end date of February 28, 2029. The original contract is dated August 11, 2025.

The motion to approve the amendment was made by Commissioner David Hildebrand and seconded by Commissioner Vincent Svec; the court recorded an unanimous vote in favor. The amendment was described in the meeting packet as a scheduling update to set a firm project end date.

County officials did not amend the contract value in the recorded motion; the court’s action set the timeline for project completion and authorizes staff to proceed under the revised schedule. The court did not record additional discussion or dissent during the vote.

Next steps: county staff will file the signed amendment with the contract record and continue project oversight through the new end date.