Selectboard approves Pay Request No. 5; town office project delayed to July 2025
Summary
The board approved Pay Request No. 5 for the Dorset Town Office project and heard that delayed delivery of timbers and trusses has pushed the expected finish to late July 2025; the building is expected to be dry by late December.
Get email alerts on the Town Office Project topic
No spam. Unsubscribe anytime.
The Dorset Selectboard approved Pay Request No. 5 for the Town Office construction project after staff presented the payment request. The motion was made by Jim Salsgiver and seconded by Frank Parent and recorded as passing 4-0 in the minutes.
Town Manager Rob Gaiotti told the board that delivery of timbers and trusses set construction back roughly four weeks; the building was expected to be 'dry' by late December with an updated projected completion in late July 2025. The minutes note that while the schedule slipped, the project remains on budget and that construction expenses will be reimbursed from the town bond for the project.