District approves $71,628 materials procurement for Hesperia Farm outfall; in-house work expected to save $500,000

Lake Arrowhead Community Services District Board of Directors · July 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board approved purchase of materials from Winwater for $71,627.89 for the Hesperia Farm outfall pipeline upsize; staff said completing the work in-house will save an estimated $500,000 compared with outsourcing.

Field Operations Manager Nathan Porter asked the Board to approve procurement of materials from Winwater for the Hesperia Farm outfall pipeline upsize in the amount of $71,627.89. Porter told the Board that the Field Operations and Mechanical Maintenance departments will perform the installation in-house, which staff estimates will save ratepayers about $500,000 compared with hiring an external contractor.

Porter noted there may be a tariff increase of 4—68% affecting final material costs. Director Jacqueline Brown moved and Vice President Steve Boydston seconded approval of the procurement; the motion carried with AYES Ambrozic, Boydston, Brown, Wurm.