Board approves $197,261 slip-lining contract for seven sewer locations to address infiltration

Lake Arrowhead Community Services District Board of Directors · July 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board awarded a contract to Insituform Technologies for Slip Lining Project No. 266 at $197,261 (15% contingency recommended) to address inflow/infiltration and root intrusion at seven locations; the project aligns with compliance under a State Water Resources Control Board cease-and-desist order.

Engineering Manager Scott Schroder presented Slip Lining Project No. 266, a targeted set of repairs at seven locations to reduce inflow and infiltration and address root intrusion in older sewer mains. Schroder said the project is part of a broader wastewater capital program and is intended to ensure compliance with an existing State Water Resources Control Board cease-and-desist order.

Two bids were received; Insituform Technologies submitted the lowest responsive bid at $197,261 compared with an engineer's estimate of $190,000. Schroder and staff recommended awarding the contract with a 15% contingency ($29,589); project funds are in Wastewater CIP Fund 210 and the project is a component of a $1.5 million program. Vice President Steve Boydston moved to award the contract and Director Jacqueline Brown seconded; the motion carried (AYES: Ambrozic, Boydston, Brown, Wurm).