Sewer and road projects: Nutter Fort engineer reports funding, timelines and outstanding permits

Town of Nutter Fort Council · March 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Engineers reported $104,818.22 remaining for a Phase IV sewer additive alternate, received contractor quotes of $132,000 and $172,000, said the LifePoint sewer is on hold, and outlined NEPA and design milestones for Phase II AMD with multiple target dates in March–April 2025 and coordination with USFWS and WVDOH.

During the March 25 meeting the town engineer updated council on multiple infrastructure projects. For Phase IV sewer work the engineer reported $104,818.22 remains for an additive alternate at Sandy’s Hardware and noted contractor quotes of $132,000 and $172,000 have been received; the engineer said right-of-way needs and a pending PSC case remain items to resolve before moving ahead.

The LifePoint sewer project is on hold while the CWSRF IUP form has been submitted. For the Route 20 corridor the contractor plans to start work in June 2025 and a future change order will be needed to account for a winter shutdown in contract time. On AMD work, Phase I closeout documents are pending; Phase II NEPA environmental assessment has been updated and will go to OSM for final approval after correspondence from the U.S. Fish and Wildlife Service. The engineer recorded design milestones: 60% conceptual design submitted 3/21/2025, 90% design targeted 4/18/2025 and final design submission 4/30/2025; mailers to residents and WVDOH coordination have started.