Summary
Johnson Engineering staff reported Lee County reviewed and approved the Cycle 4 Year 7 NPDES report (FLS000035-004); the District will file it with the Florida Department of Environmental Protection before the Nov. 1, 2024 deadline and continue into Year 8 while the new permit timing remains unclear.
Get email alerts on the Environment topic
No spam. Unsubscribe anytime.
Mark Zordan of Johnson Engineering presented the Lee County NPDES Permit FLS000035-004 Cycle 4 Year 7 Annual Report to the Board. He reported Lee County reviewed and approved the report and it will be submitted to the Florida Department of Environmental Protection in advance of the Nov. 1, 2024 deadline.
Mr. Zordan told the Board there is no definitive schedule for the new permit and staff were instructed to continue reporting into Year 8; a Johnson Engineering representative attends bi-monthly Lee County NPDES meetings and forwards minutes to the District Manager. The Board and staff discussed possible future changes to water-sampling requirements and whether stormwater ponds are subject to the same standards as natural lakes.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.