G&O reports Well 1 is producing about 330 gpm; council told maintenance may be needed

Soap Lake City Council · February 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

G&O engineer Nancy Wetch told the Soap Lake City Council that Well 1 is producing roughly 330 gallons per minute versus an expected ~1,000 gpm, and recommended maintenance or recalibration; staff will review G&O's follow-up recommendations.

Nancy Wetch of consulting firm G&O told the Soap Lake City Council that Well 1 is producing about 330 gallons per minute, well below the roughly 1,000 gallons per minute the well should be producing. "Currently this well is producing at 330 gal/minute. It should be around 1000 gal/min," Wetch said, adding that the discrepancy points to possible maintenance needs such as cleaning or equipment recalibration.

Council members discussed options for next steps and the likely need for G&O to return with a scope and cost estimate. Wetch said the immediate next step is a targeted inspection and equipment check to determine whether cleaning, recalibration, or replacement is required. No formal motion was taken during the report; Council asked staff and G&O to develop recommendations for action and potential funding paths.