District awards Phase 2 of Village Boulevard project to Silver Spur using impact‑fee funds
Summary
To comply with impact‑fee commitment deadlines, the board approved a change order to award Phase 2 of the Village Boulevard sewer project to incumbent Silver Spur Construction for about $980,794, citing engineer review and timing constraints.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The board voted to award Phase 2 of the Village Boulevard sewer project to Silver Spur Construction after staff explained that impact‑fee law requires collected impact fees be committed within six years or be returned to developers. Approving the Phase 2 change order would allow the district to commit impact‑fee funds to the project and avoid refund obligations.
Staff said Ward Engineering's estimate for Phase 2 was about $970,000 and that Silver Spur's price for the change order/Phase 2 work was approximately $980,794.15. Staff reviewed unit prices against the Phase 1 contract and noted a few line‑item adjustments (one arithmetic correction on asphalt removal, higher pipe costs, and an offsetting bypass pumping quantity). The district manager said the incumbent contractor is on-site and performing satisfactorily, which factored into the recommendation.
Board members discussed bid comparisons, timing for asphalt season, and whether awarding the work now meets the impact‑fee commitment test. Staff explained that to qualify under the impact‑fee rules the project must be under contract; given the reporting deadline and lead times for bids and construction, staff recommended approving the change order to complete the project in the coming months. A motion to award Phase 2 to Silver Spur carried unanimously.