Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Wastewater Treatment topic
No spam. Unsubscribe anytime.
Board hears wastewater‑treatment upgrade update; staff to refine cost distribution under new standards
Summary
Staff updated trustees on a state‑required wasteload analysis, bids for groundwater monitoring wells and early planning to comply with new phosphorus and ammonia standards; trustees directed staff to refine cost distribution approaches tied to impact‑fee law.
Get email alerts on the Wastewater Treatment topic
No spam. Unsubscribe anytime.
Staff told trustees they are advancing a state‑required waste‑load analysis and have solicited bids for groundwater monitoring wells to support a sewer‑treatment upgrade. Test‑well roadwork and gravel placement were under way to enable work in wet weather, and staff said those site costs would be charged to the sewer upgrade capital plan and paid by impact fees.
Trustees and staff reported a multi‑hour technical meeting with consultants to work through how to distribute costs fairly among wholesaling partners and existing users while complying with new phosphorus and ammonia standards. Staff said the issue is complex and not a straight‑line allocation; they will return with recommendations on cost distribution and impact‑fee implementation. "We got some feedback and we're working through a better distribution that is more in line with impact fee law," a staff member said. The item remains in planning; no procurement or final contract action other than the monitoring‑well authorization occurred at the meeting.
