Council to consider awarding Brant Pike lift station contract after one low bid
Summary
Public works recommended awarding the Brant Pike Lift Station construction contract to Outdoor Enterprises after receiving a single bid of $1,439,485; staff asked for a not-to-exceed amount of $1,584,000 and said funds are budgeted in the Sanitary Sewer Fund.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Public works staff recommended the city award the Brant Pike sanitary lift station construction contract to Outdoor Enterprises after a single responsive bid.
Russ, presenting the item, said the old lift station built in the 1960s cannot reliably be repaired because parts are no longer available; the new station replaces two older stations and was originally estimated at $2,000,000. “We received one quote for the project and that's Outdoor Enterprises ... they submitted a bid for $1,439,485,” Russ told council and recommended a not-to-exceed award of $1,584,000 to cover contingencies.
Staff said the project would take roughly 150 calendar days and that funds are budgeted in the Sanitary Sewer Fund. Council members asked why only one bid was received and whether the new station was sized for future growth; staff said regional contractor availability likely limited bids and that the new station was designed larger to accommodate anticipated development along the corridor.
The item will be placed on the Monday meeting agenda for formal award. No formal contract award vote occurred during the work session.