Tri Cities outlines $223.8 million plant upgrade, tank and sewer projects tied to new EPA limits
Summary
Tri Cities Wastewater Authority told Huber Heights council it will start a major plant improvement (GMP $223.8M) in August, complete sewer tie-ins this summer, and is financing work through EPA and OWDA loans with repayment projected around 2031.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Tri Cities Wastewater Authority representatives presented a multi-phase capital program to bring the regional plant into compliance with forthcoming Ohio EPA permit limits and to eliminate sanitary sewer overflows.
Danny, speaking for Tri Cities, summarized three projects: Taylorsville equalization tanks (phase 1, two 3.4M-gallon above-ground tanks completed in March at a project cost of $15,000,000); a new 30-inch dedicated Huber Heights sewer main to eliminate a hydraulic bottleneck (in progress, with Powell Road closed for a tie-in expected to finish in roughly a month and a Chambersburg Road tie-in by the end of July); and a plant improvement project whose guaranteed maximum price came in at $223,800,000 and is expected to begin construction Aug. 1 with a 4.5–5 year schedule.
“We can treat up to 4,000,000,000 with the b gallons of wastewater per year, and we see around 11,000,000 gallons per day,” Danny said while describing current flows and the share attributable to Huber Heights (about 53% of the daily flow). He told council the plant cannot meet new limits for total phosphorus, ammonia and some biochemical-oxygen-demand (BOD) thresholds, and that upgrades will increase capacity by about 64% (from approximately 11.2 million gallons to 17.3 million gallons per day).
Funding plans involve a mix of zero-percent loans previously awarded by Ohio EPA, and a construction loan at approximately 3.6% from OWDA; Danny said the authority anticipates repayment starting in about 2031 on a 30-year term for roughly $10 million per year. Tri Cities staff also said shifting operations in-house (ending a long-term Veolia contract) generated annual savings of about $600,000–$700,000 and gave the authority more operational control.
Council members pressed on master-planning and coordination with other projects (bike path routing and easements). Tri Cities confirmed the plant-improvement design reflects new permit requirements, and staff said they will return with details as bidding and financing are finalized.