Billings County authorizes East River shared-use path work and Buffalo Gap coordination with USFS

Billings County Commission · April 7, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Brosz Engineering briefed the commission on the East River Road shared-use path bid schedule and requested authorization to coordinate with the U.S. Forest Service on the Buffalo Gap Extension; the board approved moving forward and preparing a JPA with Golden Valley County with preliminary costs capped at $20,000.

Gayle Cox, a representative with Brosz Engineering, told the commission the East River Road shared‑use path "will be advertised for bids in May; bid opening anticipated late May; recommendation to the Commission expected in June." The board also heard a request to coordinate the Buffalo Gap Extension with the U.S. Forest Service and to prepare a Joint Powers Agreement with Golden Valley County, with preliminary coordination costs estimated not to exceed $20,000.

Commissioner Steven Klym moved to allow Brosz to proceed with U.S. Forest Service discussions and preparation of a JPA; Commissioner James Haag seconded and the motion carried with all voting aye. The authorization directs staff and the engineering firm to continue federal coordination and to return to the commission with the drafted JPA and any required cost updates when available.