Board authorizes bridge inspection after dryer delivery route raises safety and permitting concerns

Water Resources Board Meetings · July 30, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff told the board the planned dryer delivery involves a 150‑foot truck and trailer carrying 232,000 pounds for a single dryer; the board authorized an SSR task order to inspect and load-rate Blanton Drive bridge and explore alternate easement routes if needed.

Valerie told the board that a portion of the biosolids dryer delivery originally scheduled for mid‑August raised permitting and structural concerns because Blanton Drive bridge had not been on inspection lists and construction drawings lacked as‑built calculations. She said the dryer truck and trailer measure about 150 feet and that a single dryer load is about 232,000 pounds.

Because bridges commonly are not designed for that concentrated load, staff proposed having SSR perform an inspection and load-rating to determine whether the bridge can handle the delivery or whether an alternate plan is required. Valerie said staff would issue a letter to the contractor assigning responsibility for damages but would fund the inspection and rating to keep the project moving. She also noted an alternative easement route across Ford property from Broad Street to the plant if the bridge cannot be used; that option would require building a temporary road or other works to distribute axle loads.

The board moved to authorize a task order for SSR to inspect and provide a load rating for the bridge; the motion passed by voice vote. Valerie said staff had contacted the Tennessee Department of Transportation (TDOT), which initially considered the structure a private bridge; staff provided documentation showing the bridge serves a state right-of-way and asked TDOT to add it to routine inspections going forward.