Board approves $110,000 amendment for wet‑weather upgrades; SSR task order totals $872,060
Summary
The board approved SSR Amendment No. 3 for wet‑weather upgrades, adding $110,000 for structural repairs, a new UV channel wiring redesign and bypass pumping support, bringing SSR's task order total to $872,060 and an approximate 12% engineering fee.
Get email alerts on the Infrastructure Maintenance topic
No spam. Unsubscribe anytime.
Valerie presented Amendment No. 3 for SSR's wet‑weather improvements, explaining the work increases interim capacity and will be employed until a full expansion can be completed. She said SSR discovered UV-manufacturer wiring issues that require a revised cabling route, cracks in existing filter walls with proposed rehab methods, and the need for bypass pumping alternatives; these items led to the $110,000 amendment.
Valerie told board members the $110,000 increases SSR's task order total to $872,060 and that the engineering fee for this work sits in the 12% range relative to construction costs. She said the department will use contingency funds so the contract amount need not change, though a contract-time change order will be needed to allow the contractor to revise installation timing.
A motion to approve the amendment was moved, seconded and passed. The chair requested the staff pursue contractor nonconformance issues through the contract where clearly documented.