Commissioners choose box-culvert option for White Ash Bridge to avoid county cost-share
Summary
Wold Engineering presented two options for White Ash Bridge — three precast concrete box culverts (about $1.0M, state-funded) or an 80-foot bridge ($1.7M with $700,000 county share); the board approved the box culvert option.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
During the Aug. 19 session, Wold Engineering described two options to address the White Ash Bridge replacement. The lower-cost option recommended was three precast concrete box culverts with an estimated cost of $1.0 million and anticipated to be 100% state funded; the alternative was an 80-foot bridge estimated at $1.7 million that would require a county cost share of approximately $700,000 because of additional grade raise, earthwork and railings. The board voted to approve the box culvert option, which Wold Engineering advised would avoid a county cost share.
The transcript shows the board weighed the cost-share implications before voting. The decision was recorded as a unanimous motion in the Aug. 19 minutes; the county will proceed with project steps consistent with the chosen option and the preconstruction schedule already set for related park access work.