Advisory committee limits Lake St. Helen fixes to $50,000; engineers recommend flop and crane-operated gates
Summary
Roscommon County officials said the Lake St. Helen advisory committee does not want to exceed $50,000 for fixes; engineers recommended a center flop gate plus two gates serviced by crane for high-water events.
Get email alerts on the Lake St. Helen topic
No spam. Unsubscribe anytime.
At the Roscommon County special meeting May 13, commissioners reported that the Lake St. Helen advisory committee has set a spending preference of no more than $50,000 for control-structure work. County officials said water levels are coming down and that preliminary engineering conversations considered a center "flop" gate and two gates that would be lowered or raised by crane when lake levels are high.
No formal procurement or contract award took place at the meeting; the advisory committee's $50,000 limit will guide next steps as staff and consultants refine designs and cost estimates. Commissioners did not specify whether the $50,000 cap includes permitting, crane rental, or ongoing maintenance costs.