Parish reallocates library funds: Lacombe replacement and Slidell expansion receive multimillion‑dollar increases
Summary
Capital Amendment No. 13 increases budgets for the Lacombe branch replacement and the Slidell branch expansion and shifts $100,000 from a parish‑wide technology project to Slidell.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Annie reviewed Capital Amendment No. 13 (Ordinance calendar No. 81‑63), which carries three library projects.
The Lacombe branch replacement is an amendment of $3,750,000 for additional design and construction work; Annie said the total project budget will be $4,050,000. For the Slidell branch expansion, the amendment is $3,850,000 for architectural/design services and construction at 555 Robert Boulevard, bringing that project's total to $4,150,000. Annie also said the parish will decrease a parish‑wide technology upgrade by $100,000 and transfer that amount to the Slidell project.
Councilman Laughlin asked whether library millage funds are restricted to library system use; Annie confirmed the dollars come from an ad valorem millage dedicated to the library system. A staff member asked Daniel Hill about design progress; the response reported both library projects' design phases are more than halfway complete and that the parish expects to go out for construction bids toward the end of the year.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.