Creek Drive water-main replacement planned with 3 hydrants and EGLE permit in place

Special Council Meeting · July 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Creek Drive project will replace roughly 1,150 linear feet of 4-inch cast-iron main with 6-inch PVC and add three fire hydrants; the village has completed SHPO review and holds an EGLE construction permit for this segment, with NIES Engineering to assist during bidding.

Council materials presented at the July 25 meeting describe the Creek Drive water-main replacement as roughly 1,150 linear feet of new 6-inch PVC main from Chickagami Trail to Grand Beach Road and the installation of three fire hydrants. The village has completed State Historic Preservation Office (SHPO) review for the project and holds an EGLE construction permit for Creek Drive, according to the meeting record.

NIES Engineering's scope for Creek Drive is limited to assistance during the bid process; the firm will help the village re-bid the work product owned by the village that was previously designed and bid by others. The council approved proceeding with NIES subject to attorney review and a $24,000 cap on fees. Bids are targeted for early September so construction can commence this fall, per the council's timeline.