Tecumseh council approves change order and final pay for power plant cooling project

City Council of the City of Tecumseh, Nebraska · December 1, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a $44,863.75 decrease (Change Order #2) and a final pay application of $246,433.63 to Farabee Mechanical for the power plant cooling project; motions carried unanimously.

The Tecumseh City Council approved Change Order #2 for the Power Plant Cooling Project, a reduction of $44,863.75, and authorized final payment to Farabee Mechanical in the amount of $246,433.63. The motions were moved by Council member Lorie Topp and seconded by Brian Britt and carried with all present council members voting aye.

During the utility department report, staff noted the cooling project is substantially complete and that state reimbursement timing had been affected by a government shutdown but was improving. The minutes do not record outstanding punch-list items; final payment and the change order indicate the project is moving to closeout and that the council approved contractor final payment.