Board accepts $133,271 GMP amendment to replace lagoon slide gates with weir gates
Summary
Fayette County accepted a Guaranteed Maximum Price amendment to replace slide gates with weir gates at lagoons, adding $133,270.92 in costs; installation is scheduled to be completed by July 1, 2026.
Get email alerts on the Wastewater Management topic
No spam. Unsubscribe anytime.
The Fayette County Board of Commissioners accepted an amended Guaranteed Maximum Price (GMP) amendment from Bowen Engineering Corporation on March 9 to replace slide gates at wastewater treatment lagoons with weir gates. The minutes record construction cost of $123,399.00, CMAR fee of $5,864.45, and contingency $4,010.47 for a total change order cost of $133,270.92. Work is scheduled for completion by July 1, 2026.
Commissioners said the county operations team determined the replacement would better serve operations. The amendment was accepted by unanimous roll call and the complete amendment is on file with the county.