District facility report: Park Side redesign goes to bid; CalSHAPE plumbing project will replace dozens of fixtures
Summary
Facilities staff reported a SunRidge Fire Marshal walkthrough, a Park Side office redesign going to bid with higher costs for electrical and ADA work, and CalSHAPE-funded plumbing work replacing 40 toilets, 4 urinals and 33 faucets and installing 51 CO2 monitors.
Get email alerts on the Facility Updates topic
No spam. Unsubscribe anytime.
The Board reviewed a facilities update that included several active projects and upgrades that affect school buildings and site operations.
Sara Gramm told trustees that Brent Ono completed a SunRidge walkthrough with the Fire Marshal and that Blitz Architecture is finalizing plans for the Park Side office redesign; the project will go out to bid but costs are higher than originally anticipated because of additional electrical and ADA upgrades. Separately, the district's CalSHAPE plumbing project will replace 40 toilets, 4 urinals and 33 faucets and add 51 CO2 monitors across district facilities.
Trustees were also briefed on event coordination plans, including a Park Side light show project and neighbor notifications. The minutes do not list contract amounts or bid timelines; staff will proceed with bidding and required inspections.